Flat renovation, Długa 5, Kraków
Summary
According to Oleh, two coats of skim plaster were applied to all walls in the room and sanding has started. The owner asked to change the tile colour to dark grey, but that material is not in stock. A problem with the electrics was also reported: the sockets were installed differently from the plan. Planned for tomorrow: priming, painting the walls and fitting the skirting boards.
Tasks
- Check the socket positionshigh priority
- Agree the tile colour change with the supplierby Friday
- Agree the work handover with the inspectoron Friday
- Prime and paint the wallstomorrow
- Fit the skirting boardstomorrow
Photos
Water connectionsInstalled and marked, ready to be closed in.
Wall socketSockets set into the wall, to be checked against the plan.
Door openingFrame fitted and prepared for plaster.
Recording excerpt
«Добрий день, Олег на зв’язку, об’єкт на Długiej 5. Сьогодні в кімнаті наклали гладь шпаклівкою на всіх стінах, два шари, і почали шліфувати. Власник просив поміняти колір плитки на сірий графіт, але на складі її немає.»
Translation: Hello, Oleh here, the site at Długa 5. Today in the room we applied skim plaster to all the walls, two coats, and started sanding. The owner asked to change the tile colour to dark grey, but it is not in stock.
Download PDF